<< Click to Display Table of Contents >> Projected Completion Report |
![]() ![]()
|
The Projected Completion Report provides information on work-in-process transactions that are posted in the system but are not yet finished.
This report has the following uses:
•To serve as reference in identifying the number of days to complete the work orders that are still in process
•To serve as reference in prioritizing the completion of work orders and planning the availability of resources to complete the work orders
To generate the Projected Completion Report, perform the following steps:
1.Access the Projected Completion Report function from the Production group under the Reports main menu in Manufacturing module.
2.Click the List box button beside the Configuration field and select the preferred report configuration.
3.Amend or accept the default sorting option in the Sort By field. To select a different Sort By option, click the List box button and select from the options displayed on the list.
4.In the Layout field, accept or amend the default layout for the report. To select a different Layout option, click the List box button and select from the options displayed on the list.
5.In the Report Configuration area, define the report filters. Depending on the Sort By option you choose, you may mark the Individual checkbox if you want to generate the report for a single record and enter the appropriate value in the adjacent field; otherwise, select in the Filters area the preferred criteria in generating the report.
6.Click the Preview or Print button to preview or print the report, respectively.
The Projected Completion Report function provides you with flexibility to perform the following:
•Set up user-defined report macro
•Set up user-defined sort option
•Set up user-defined report layout
•Include notes in the printed report
•Export the report to various supported file formats
•Send the report as attachment to an email
•Include time and printed by information
© 2023 AccountMate Software Corporation